How Long Does Windows & Doors Take? Timelines and What to Expect
The window you pick from a showroom sample is rarely in stock. Custom-sized windows for older San Francisco homes, where openings are almost never standard, routinely run 6 to 12 weeks from order to delivery. That’s before a single tool touches your wall. Most homeowners plan around the install day and forget the eight weeks that come before it. This guide breaks a window and door replacement into every phase it actually has: measuring, ordering, permitting, delivery, installation, and finishing, with realistic calendar time for each, plus the San Francisco quirks that stretch timelines and the contract language that keeps a job on schedule.
Quick Answer
A typical window or door replacement in San Francisco takes 10 to 16 weeks from signed contract to final walkthrough. Custom order and delivery eat 6 to 12 weeks, permit review adds 2 to 6 weeks depending on scope, and installation itself runs one to three days for a single door and one to two weeks for a whole-house window package. Standard in-stock sizes move much faster, often 2 to 4 weeks total.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
Table of Contents
- The Five Phases of a Window and Door Project
- How Long Does Measuring and Ordering Take?
- How Long Do Permits Take in San Francisco?
- Why Delivery Timelines Slip
- How Long Does Installation Itself Take?
- Why Pre-1940 San Francisco Homes Take Longer
- Sequencing a Whole-House Replacement
- Legitimate Delays vs. Contractor Failures
The Five Phases of a Window and Door Project
Every replacement moves through the same five phases. Understanding them separately is the only way to spot where a job stands and whether a promise is realistic. Here’s the breakdown.
1. Measuring and ordering
A technician measures every opening, confirms the frame condition, and submits the order to the manufacturer. For custom sizes, this is the single longest phase. Expect 6 to 12 weeks for European tilt-turn or architectural-grade windows, and 3 to 6 weeks for semi-custom. Andersen and Marvin custom orders routinely land toward the longer end. Stock sizes ship in days.
2. Permit pulling
San Francisco requires a permit for most window replacements that alter the opening, change egress, or touch a street-facing facade in a historic district. Plan on 2 to 6 weeks for SFDBI review, longer if the property is in a Historic Resource area or the scope triggers Planning Department review.
3. Delivery
Manufacturers give a ship date, not a delivery-to-site date. Actual arrival to your driveway can lag another one to two weeks depending on freight scheduling and whether a crew needs to be on site to receive.
4. Installation
One door: one to three days. Ten to twenty windows: one to two weeks. Whole-house packages: two to four weeks.
5. Finishing and inspection
Trim, caulk, paint touch-up, plaster repair inside, and the final building inspection. Budget three to ten days after the last unit goes in.
How Long Does Measuring and Ordering Take?
Measuring is fast. Ordering is not. A technician can measure a full house in three to five hours. Turning those measurements into a confirmed manufacturer order is where the calendar disappears.
Here’s what actually drives the wait:
- Custom sizing. Older San Francisco homes almost never have standard rough openings. Every unit becomes a one-off build.
- Color and finish. Non-white exterior colors add two to four weeks at most manufacturers. Custom-matched clad or bronze finishes add more.
- Glass packages. Low-E, laminated, or impact-rated glass is a special order on most lines. Standard dual-pane moves faster.
- Brand backlog. Andersen and Marvin offer premium product lines with real quality advantages, but their custom lead times fluctuate with factory capacity.
The mistake is signing a contract before the order is confirmed. Ask for the manufacturer’s acknowledgment in writing with a firm ship date before you sign. That one document prevents the “we’re waiting on the factory” conversation three months later. For a full-scope project that combines doors with other structural work, our team can align the window schedule with the rest of the build through our Groundwork Construction Co. of San Francisco home services.
How Long Do Permits Take in San Francisco?
Permit review is the variable most homeowners underestimate. It’s also the most common reason a job stalls for weeks without anyone having picked up a hammer.
SFDBI processes standard residential window permits in roughly 2 to 6 weeks. What pushes that longer:
- Historic district review. Properties in a Historic Resource area or a neighborhood with Article 10 or Article 11 status need Planning Department sign-off before SFDBI will issue. That adds 4 to 12 weeks.
- Facade change. Changing window style on a street-facing wall, replacing single-hung with casement, or altering visible trim can trigger design review.
- Egress windows. Any window serving as a bedroom egress must meet current California code for clear opening size. If the existing opening doesn’t comply, the replacement can require a scope addition.
- Complete applications. A missing site plan or unclear scope of work can add a two-week resubmittal cycle manually.
Pulling permits and passing inspections is a core part of the Groundwork process, not an add-on. The reason is simple: starting a job you can’t legally complete on schedule creates a bigger delay than waiting a few extra weeks on the front end. If your property sits in a historic overlay, expect the permit phase to dominate the schedule and plan accordingly. For projects that pair window replacement with structural or addition work, our Home Additions & ADU in San Francisco team coordinates permits across scope in one application.
Why Delivery Timelines Slip
The factory ships windows on a freight carrier, not a courier. That distinction matters for anyone planning around a specific install date.
A manufacturer’s ship date is the day the product leaves the plant. Delivery to your home can lag another one to two weeks depending on:
- Freight scheduling. Carriers consolidate loads. Windows sit in a transfer hub until a truck is heading your way.
- Receiving logistics. Someone has to be on site to inspect and sign for the delivery. Damage in transit should be caught at the moment of delivery, not a week later.
- Site access. Narrow San Francisco lots, steep streets, and tight garage clearances affect the delivery truck’s ability to unload. A van-ready crew is different from a tractor-trailer-ready driveway.
- Weather windows. A window order arriving in February when the site is soaked from an atmospheric river means staging in place and waiting for install-ready conditions.
Ask your contractor to build two weeks of float into the schedule between the ship date and the install start. If the delivery arrives early, the job starts early. If it slips, the schedule absorbs the hit. That’s not pessimism; it’s planning. Every trades person on the project is affected if the windows show up late.
How Long Does Installation Itself Take?
Installation is the shortest phase of the project and the one most people picture when they sign the contract. Here are realistic durations.
| Scope | Typical install time |
|---|---|
| Single replacement window | 2 to 4 hours |
| Single entry or patio door | 1 to 3 days |
| 5 to 10 windows | 3 to 5 days |
| 10 to 20 windows | 1 to 2 weeks |
| Whole-house window package | 2 to 4 weeks |
Doors take longer than windows because they involve framing, threshold work, hardware tuning, and a weather-tight seal that has to survive San Francisco’s wind-driven rain in the Outer Sunset and Pacifica-facing neighborhoods.
Installation is also where detailed finish work happens: trim, caulk, interior plaster touch-up, and paint. Plaster walls in Richmond and Mission District homes are notorious for needing patching after a window cut. If your installer treats finishing as a fast afterthought, you’ll see cracks and hairline gaps a month later. Finishing is part of installation, not a separate phase. For complete replacement of doors and windows during a broader home improvement project, pairing the schedule with fencing and exterior work can help coordinate installations, as detailed in our Fence Installation in San Francisco guide.
Why Pre-1940 San Francisco Homes Take Longer
Roughly 40% of San Francisco’s housing stock was built before 1940. That single fact reshapes the timeline for most replacement projects in the city.
Three structural realities come up constantly:
Non-standard rough openings
Old homes were built by hand with whatever materials the site had. No two openings are identical. A modern replacement unit is manufactured to the measurement taken, not a standard size, which pushes every order into the custom category. A house that looks uniform from the curb can have twenty different opening dimensions.
Balloon framing
Many pre-1940 San Francisco homes use balloon framing, where studs run continuously from the foundation to the roof. Removing a window during install sometimes reveals fire-blocking gaps, insulation voids, or a header that isn’t where the drawing suggested. Structural surprises add days or weeks. If your project crosses from window work into anything structural, our Home Additions & ADU in San Francisco page covers how those surprises are handled in a full-scope build.
Plaster wall restoration
Lath-and-plaster walls crack around a replacement opening and don’t patch the way drywall does. A trained finisher patches, feathers, primes, and paints. This adds two to five days per room and shouldn’t be skipped. Leaving the plaster raw in an area with an exterior wall can lead to moisture issues.
Weather is the fourth factor. San Francisco’s fog belt, winter rain, and seasonal wind mean installs happen on a weather-aware schedule. A day of rain in January is a lost install day, not a “we’ll work through it” day, because sealing the opening properly requires dry conditions.
Sequencing a Whole-House Replacement
Replacing every window in a home isn’t one project; it’s a sequence of small ones. The right order protects the house in the meantime.
A practical sequencing plan:
- Start with the rooms you don’t use daily. A guest room or spare bedroom lets the crew learn the house without disrupting your routine.
- Work one wall at a time, not one window at a time. Completing a wall at once keeps the exterior weather-tight and prevents a half-finished facade from sitting through rain.
- Never remove more than two openings at once. A windowless wall overnight invites water infiltration and both security and safety risk during a changeover period. A crew you hire for every job should know this.
- Do the front facade last. This is the wall passing neighbors and potential appraisers will notice first. Keep it finished and intact.
- Keep the primary bedroom and living room functional until the end. You’re not moving out of your home for a whole-house replacement, but staying in your routine matters for the reality of living through a project.
Security is the other half. During a whole-house replacement, some windows are open to the outside for hours. A contractor who plans the sequence around weather forecasts and locks up at the end of every day is not being overly cautious. For homes with exterior security gates or side-yard access, scheduling coordination with our Driveway & Pavers in San Francisco installation may be part of the same overall project.
Legitimate Delays vs. Contractor Failures
Some delays are unavoidable. Others are a scheduling choice. Knowing the difference before you sign is how you protect your project.
Legitimate delays
- Factory slip. Manufacturer extends its ship date due to material shortages or capacity limits. This is real and documented.
- Weather. Rain, high wind, or an unusually cold snap stops install work until conditions allow proper sealing.
- Permit review. SFDBI asks for additional information or the property falls into a historic overlay. This is a calendar reality, not a contractor problem.
- Discovery during demolition. Opening the wall reveals a rotted header, a hidden vent, or old knob-and-tube wiring that has to be resolved before finishing. Good contractors document this in writing with photos.
Contractor failures
- The crew was double-booked. Your install date slips because another job started first. This isn’t a delay; it’s a scheduling choice made against you.
- The order was placed late. The contract was signed in January but the manufacturer didn’t get the order until March. That’s an internal process failure.
- The permit was never pulled. If a contractor starts work before the permit is issued, the inspection fails and the project has to stop until paperwork catches up.
- No written change-order process. Scope expands without documentation, and the schedule becomes a vague guess instead of a plan.
The way to build accountability into the contract is simple. Require written confirmation of the manufacturer order date, ship date, permit application date, and install start. Require a written change-order process for any surprise discovered during work. Require a completion holdback that only releases after final inspection. Groundwork backs every project with the 730-Day Done Right Promise, so if it’s not done right, we make it right, for a full two years. That’s a workmanship guarantee that lives on paper, not in a brochure.
Common Mistakes to Avoid
- Signing before the manufacturer confirms the order. A signed contract with no factory acknowledgment date is a promise with no delivery behind it. Get the manufacturer’s written ship date before you sign.
- Forgetting permit timelines in the schedule. If the permit takes six weeks and your schedule has four, the install stalls. Build the permit phase into the calendar, not the afterthought.
- Ordering custom windows as if they’re stock. In pre-1940 San Francisco homes, almost every opening is custom. Budgeting three weeks for a custom order is the single biggest planning error we see.
- Choosing the cheapest installer with no finishing scope. Plaster restoration, trim, caulk, and paint add real time. A bid that skips finishing isn’t a shorter project; it’s a longer one with three weeks of follow-up.
- Installing during an active rain stretch. A window frame that’s open to a storm for twelve hours invites water intrusion and mold risk. Waiting five days for a dry window is cheaper than addressing water damage later.
- Removing too many windows at once during whole-house work. More than two openings at a time leaves the home exposed and harder to secure overnight. Sequence the job so the house stays intact throughout.
- Skipping a written change-order process. When a hidden structural issue surfaces, a job with no paperwork protocol ends up haggling over schedule for a month. Put it in writing up front.
See the difference
Before
After
Before
After
Before
AfterWhen to Call a Professional
If you’re replacing a single window and you’ve done it before, you may be able to handle stock sizes. When the work crosses into any of these areas, it’s time to call:
- A whole-house window or door package where sequencing, permits, and weather protection all interact
- Any pre-1940 San Francisco home with suspected balloon framing or structural issues behind the opening
- Doors serving as egress or on a street-facing facade in a historic district
- A project combined with roofing, additions, or exterior work so the schedules interlock
- A manufacturer order that came in damaged or sized wrong and needs to be reordered with a documented claim
Groundwork Construction Co. of San Francisco offers free estimates in San Francisco and answers the phone with a live person, 24 hours a day. Call (866) 320-2646 to schedule a walkthrough. Our technicians have up to 12 years of experience, arrive background-checked and in uniform, and every project is backed by the 730-Day Done Right Promise.
Frequently Asked Questions
Expect 12 to 20 weeks from signed contract to final inspection for a whole-house package in San Francisco. The bulk of that is custom ordering (6 to 12 weeks) and permit review (2 to 6 weeks). Actual install time is 2 to 4 weeks. Standard-size stock windows move much faster, often within 4 to 6 weeks total. Call (866) 320-2646 for an estimate specific to your opening count and property.
In most cases yes. San Francisco requires a permit when you alter an opening, change window style in a way that affects egress or the facade, or work in a historic district. Like-for-like replacements of identical size in some cases qualify for simplified review. Always confirm with SFDBI before starting, and never begin work before the permit is issued. Estimates are free at (866) 320-2646.
A single stock-size window can be installed in a few hours. A whole-house project cannot. Cutting and finishing the opening, flashing, caulking, trim, plaster restoration, and paint take real time. A crew promising a full-house install in one day is skipping finishing. Call (866) 320-2646 to schedule a realistic walkthrough and written scope.
It can, but a well-planned job shouldn’t shift without a documented reason. Hidden damage behind an opening, an extended factory delay, or a permit review addition are legitimate changes. A crew being double-booked, late ordering, or skipping a permit is not. A written contract with a change-order process and confirmed order dates keeps the schedule honest. Groundwork’s 730-Day Done Right Promise applies to the workmanship through the whole timeline.
An entry door install typically runs one to three days, plus a custom order lead time of 4 to 10 weeks depending on the door line. Hardware, threshold, and weather sealing take most of the on-site time. Anything in a street-facing historic district adds permit weeks. Call (866) 320-2646 for a specific timeline on your door.
We work with a curated set of verified brand partners across the trades, including Andersen and Marvin for windows, and quality door hardware from brands such as Sterling and Grohe for interior fixtures. Brand availability affects lead times, and we’ll quote the delivery window for each line before you sign. Call (866) 320-2646 for a brand and timeline comparison.
The Bottom Line
Window and door replacement in San Francisco takes longer than almost any contractor will tell you on the first walkthrough, not because the install is slow but because custom ordering, permit review, and old-home quirks absorb most of the calendar. Plan on 10 to 16 weeks for a standard single-family home, and 12 to 20 weeks for a whole-house package. Build two weeks of float into the schedule, confirm the manufacturer’s ship date in writing before you sign, and require a written change-order process. Every project backed by the 730-Day Done Right Promise carries the same standard from first measurement to final inspection, with no-hassle upfront pricing so the number you see is the number you pay, plus $1,000 off projects over $10,000 and 0% financing for 18 months.